Pre-Start Meeting
Safety Notification: No individuals are to remove, adjust or alter any scaffold, propping or temporary structures under any circumstances. Without first receiving direct written permission from EMCO’s Site Management team. Always check with EMCO Site Management if you have any questions or concerns regarding scaffold, propping or temporary structures.
SITE ACTIVITIES
Framing, Sheeting and flushing of walls to various levels
Mechanical ductwork install to level 1
Formwork to various areas on GF-Level 3
Brickwork to level 1
Erection of perimeter scaffold , shade cloth
Structural steel install to lintels and perimeter angle to level 1
Fire and water services in basement to level 2
Fire Door Install to basement
CONTROLS
-No parking permitted at front car bays , all trades to park at designated area
-Exclusion zones to be maintained in high risk activity areas - Keep to designated pedestrian pathways & look out for mobile plant, trucks and warning signs.
-Trucks reversing into site require a spotter
-Hi Vis to be worn at all times
-Do not alter, remove any hop ups or handrails without Site Managers approval -
30th Eylül 2024, Pre Start Meeting September 30, 2024
Pre-Start Meeting
Safety Notification: No individuals are to remove, adjust or alter any scaffold, propping or temporary structures under any circumstances. Without first receiving direct written permission from EMCO’s Site Management team. Always check with EMCO Site Management if you have any questions or concerns regarding scaffold, propping or temporary structures.
SITE ACTIVITIES
Framing, Sheeting and flushing of walls to various levels
Mechanical ductwork install to level 1
Formwork to various areas on GF-Level 3
Brickwork to level 1
Erection of perimeter scaffold , shade cloth
Structural steel install to lintels and perimeter angle to level 1
Fire and water services in basement to level 2
Fire Door Install to basement
CONTROLS
-No parking permitted at front car bays , all trades to park at designated area
-Exclusion zones to be maintained in high risk activity areas - Keep to designated pedestrian pathways & look out for mobile plant, trucks and warning signs.
-Trucks reversing into site require a spotter
-Hi Vis to be worn at all times
-Do not alter, remove any hop ups or handrails without Site Managers approval
Geçerli Saha Hava Durumu
Son Güncelleme Saati: 17:31
Sıcaklık: 20C (App 17C)
Rüzgar Hızı: 19KMH
Maks. Rüzgar: 22KMH @14:21
Saat 9'dan beri yağmurlu: 0,0mm
Min Sıcaklık: 17C @07:09
Maks Sıcaklık: 26C @12:49 20.11.2024
Bora: 28KMH
Maks Bora: 30KMH @13:21
Gözlem Konumu - Perth, WESTERN AUSTRALIA
Zaman Dilimi - Batı Avustralya Standart Saati
Tahmin - Perşembe, 21 Kasım
Mostly sunny.
Min: 13C Maks: 24C
Yağmur İhtimali: 10%
Tahmin Konumu - Perth, WESTERN AUSTRALIA
Zaman Dilimi - Batı Avustralya Standart Saati
Yarın - Cuma, 22 Kasım
Sunny.
Min: 14C Maks: 27C
Yağmur İhtimali: 0%
Bu sahanın KKD Gereksinimlerini biliyor musunuz?
Sahadaki ilk gününüzde doğru güvenlik ekipmanlarına sahip olduğunuzdan emin olun.
Sahaya geldiğinizde kısa süre içinde çalışmaya başlamak için hazırlanın.
Saha kaydınızı çevrimiçi tamamlayın ve zamandan kazanın.
Bu sahanın KKD Gereksinimlerini biliyor musunuz?
Sahadaki ilk gününüzde doğru güvenlik ekipmanlarına sahip olduğunuzdan emin olun.
Sahaya geldiğinizde kısa süre içinde çalışmaya başlamak için hazırlanın.
Saha kaydınızı çevrimiçi tamamlayın ve zamandan kazanın.