MELVISTA - Veřejná stránka projektu
-
03rd října 2024, Pre Start Meeting October 3, 2025
Pre-Start Meeting
Safety Notification: No individuals are to remove, adjust or alter any scaffold, propping or temporary structures under any circumstances. Without first receiving direct written permission from EMCO’s Site Management team. Always check with EMCO Site Management if you have any questions or concerns regarding scaffold, propping or temporary structures.
SITE ACTIVITIES
Framing, Sheeting and flushing of walls to various levels
Mechanical ductwork install to level 1
Formwork to various areas on GF-Level 3
Brickwork to level 1
Erection of perimeter scaffold , shade cloth
Structural steel install to lintels and perimeter angle to level 1
Fire and water services in basement to level 2
Fire Door Install to basement
CONTROLS
-No parking permitted at front car bays , all trades to park at designated area
-Exclusion zones to be maintained in high risk activity areas - Keep to designated pedestrian pathways & look out for mobile plant, trucks and warning signs.
-Trucks reversing into site require a spotter
-Hi Vis to be worn at all times
-Do not alter, remove any hop ups or handrails without Site Managers approval -
30th září 2024, Pre Start Meeting September 30, 2024
Pre-Start Meeting
Safety Notification: No individuals are to remove, adjust or alter any scaffold, propping or temporary structures under any circumstances. Without first receiving direct written permission from EMCO’s Site Management team. Always check with EMCO Site Management if you have any questions or concerns regarding scaffold, propping or temporary structures.
SITE ACTIVITIES
Framing, Sheeting and flushing of walls to various levels
Mechanical ductwork install to level 1
Formwork to various areas on GF-Level 3
Brickwork to level 1
Erection of perimeter scaffold , shade cloth
Structural steel install to lintels and perimeter angle to level 1
Fire and water services in basement to level 2
Fire Door Install to basement
CONTROLS
-No parking permitted at front car bays , all trades to park at designated area
-Exclusion zones to be maintained in high risk activity areas - Keep to designated pedestrian pathways & look out for mobile plant, trucks and warning signs.
-Trucks reversing into site require a spotter
-Hi Vis to be worn at all times
-Do not alter, remove any hop ups or handrails without Site Managers approval
Aktuální počasí na pracovišti
Naposledy aktualizováno v: 16:21
Teplota: 21C (Aplikace 18C)
Rychlost větru: 19KMH
Max. vítr: 22KMH @14:21
Déšť od 9 ráno: 0,0mm
Min. teplota: 17C @7:09
Max. teplota: 26C @12:49 20.11.2024
Náraz větru: 28KMH
Max náraz větru: 30KMH @13:21
Místo pozorování - Perth, WESTERN AUSTRALIA
Časové pásmo - západoaustralský standardní čas
Předpověď – čtvrtek, 21 listopadu
Mostly sunny.
Min: 13C Max: 24C
Možnost deště: 10%
Místo předpovědi – Perth, WESTERN AUSTRALIA
Časové pásmo - západoaustralský standardní čas
Zítra - pátek, 22 listopadu
Sunny.
Min: 14C Max: 27C
Možnost deště: 0%
Znáte požadavky na OOPP pro toto pracoviště?
Ujistěte se, zda máte pro první den na pracovišti správné bezpečnostní vybavení.
Po příjezdu na místo můžete začít pracovat dříve.
Jakmile budete moci, dokončete registraci do pracoviště online, a ušetřete si tak čas.
Znáte požadavky na OOPP pro toto pracoviště?
Ujistěte se, zda máte pro první den na pracovišti správné bezpečnostní vybavení.
Po příjezdu na místo můžete začít pracovat dříve.
Jakmile budete moci, dokončete registraci do pracoviště online, a ušetřete si tak čas.