MELVISTA - Cantiere del progetto pubblico
-
03rd ottobre 2024, Pre Start Meeting October 3, 2025
Pre-Start Meeting
Safety Notification: No individuals are to remove, adjust or alter any scaffold, propping or temporary structures under any circumstances. Without first receiving direct written permission from EMCO’s Site Management team. Always check with EMCO Site Management if you have any questions or concerns regarding scaffold, propping or temporary structures.
SITE ACTIVITIES
Framing, Sheeting and flushing of walls to various levels
Mechanical ductwork install to level 1
Formwork to various areas on GF-Level 3
Brickwork to level 1
Erection of perimeter scaffold , shade cloth
Structural steel install to lintels and perimeter angle to level 1
Fire and water services in basement to level 2
Fire Door Install to basement
CONTROLS
-No parking permitted at front car bays , all trades to park at designated area
-Exclusion zones to be maintained in high risk activity areas - Keep to designated pedestrian pathways & look out for mobile plant, trucks and warning signs.
-Trucks reversing into site require a spotter
-Hi Vis to be worn at all times
-Do not alter, remove any hop ups or handrails without Site Managers approval -
30th settembre 2024, Pre Start Meeting September 30, 2024
Pre-Start Meeting
Safety Notification: No individuals are to remove, adjust or alter any scaffold, propping or temporary structures under any circumstances. Without first receiving direct written permission from EMCO’s Site Management team. Always check with EMCO Site Management if you have any questions or concerns regarding scaffold, propping or temporary structures.
SITE ACTIVITIES
Framing, Sheeting and flushing of walls to various levels
Mechanical ductwork install to level 1
Formwork to various areas on GF-Level 3
Brickwork to level 1
Erection of perimeter scaffold , shade cloth
Structural steel install to lintels and perimeter angle to level 1
Fire and water services in basement to level 2
Fire Door Install to basement
CONTROLS
-No parking permitted at front car bays , all trades to park at designated area
-Exclusion zones to be maintained in high risk activity areas - Keep to designated pedestrian pathways & look out for mobile plant, trucks and warning signs.
-Trucks reversing into site require a spotter
-Hi Vis to be worn at all times
-Do not alter, remove any hop ups or handrails without Site Managers approval
Meteo attuale del cantiere
Ultimo aggiornamento su: 05:21
Temperatura: 15C (App 15C)
Velocità del vento: 9KMH
Max. Vento: 9KMH @05:21
Pioggia dalle 9.00: 28,4mm
Temp min: 15C @05:01
Temp max: 23C @11:14 03/06/2025
Raffica: 11KMH
Raffiche max: 11KMH @05:21
Luogo di osservazione - Perth, WESTERN AUSTRALIA
Fuso orario - Ora standard dell’Australia occidentale
Previsioni - mercoledì, 4 giugno
Showers easing.
Min: 12C Max: 20C
Possibilità di pioggia: 90%
Precipitazioni previste: 1 a 9mm
Luogo previsioni - Perth, WESTERN AUSTRALIA
Fuso orario - Ora standard dell’Australia occidentale
Domani - giovedì, 5 giugno
Partly cloudy.
Min: 8C Max: 19C
Possibilità di pioggia: 10%
Conosci i requisiti dei DPI per questo cantiere?
Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.
Inizia a lavorare prima quando arrivi sul cantiere.
Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.
Conosci i requisiti dei DPI per questo cantiere?
Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.
Inizia a lavorare prima quando arrivi sul cantiere.
Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.